TCN commissions new 300MVA, 330/132KV power transformer at Katampe Sub-Station

By: Jabiru Hassan.

The Transmission Company of Nigeria (TCN) has commissioned a 300MVA 330/132kV power transformer at its Katampe 330/132/33kV Transmission Substation, Abuja, on Sunday, 24th May 2026.

With the commissioning of the new 300MVA power transformer, the substation’s capacity has increased from 450MVA to 750MVA.

The upgrade means TCN now has more power available at Katampe Substation for Abuja Electricity Distribution Company (AEDC) to offtake for onward distribution to consumers in Abuja and environs. 

Speaking at the commissioning ceremony, the General Manager (Transmission), Abuja Region, Engr. Musa Shuaibu, noted that the installation and commissioning of the transformer underscores TCN’s commitment to the continuous expansion of the transmission network.

This, he said, will support increased power delivery, enhance overall grid stability, and facilitate better electricity supply to distribution load centers nationwide.  

The project was executed under the TCN-World Bank collaborative initiative, which is part of strategic efforts to rehabilitate and expand the nation’s transmission network.

Tags

Share this post:

Leave a Reply

Your email address will not be published. Required fields are marked *

em ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur.